Houston-based Targa Resources said recently it is ordering long-lead equipment for an additional natural gas processing plant in Midland Basin and two additional processing plants in Delaware Basin. Jen Kneale, president, said Nov. 5, “We are evaluating the timing and expect these new plants will likely be needed in 2028 or early 2029.”
Targa said its Copperhead plant in Delaware Basin (275 million cfd) is currently in start-up (ahead of schedule). The company expects its Yeti and Yeti II plants (each 275 million cfd) to begin operations in Q2 and Q3 next year (earlier than expected). And construction continues on Roadrunner III, Copperhead II, Wrangler, Ranger and Ranger II plants in Delaware Basin.